Hi all.
Could any one helps me with the following:
If the integration of CO-FM is activated in V_FM01_CO_INTEGR and the date for activating of the integration CO-FM for HR is in the past for example 01/01/2007 the fields funds center and commitment item are hiden in the HR screens (IT 0001, 0027) for all records since 01/01/2007. But you can manually maintain these fields for all records wich endda is 12/31/2006.
I want to maintain the funds center in IT0001 always, so I donu2019t fill the date which means that I donu2019t want to activate the integration CO-FM for HR and want to maintain manually the fields mentioned above.
In the table V_T001_FM3 I set the date 01/01/1990 for the field "Funds center in HR".
After that the field Funds center is appeared in IT0001 for maintaining but when you set the value the message comes
"Account assignment Funds Center is inactive in HR on 18.12.2009 and must therefore be empty"
I think here is an error.
Best regards,
Alice.
Edited by: Alice Oganesyan on Mar 10, 2010 10:38 AM
Edited by: Alice Oganesyan on Mar 10, 2010 10:48 AM
Edited by: Alice Oganesyan on Mar 10, 2010 10:48 AM